Cost-Schedule

KEY FACTS & FIGURES


BRONSON

MARKET-RATE MULTIFAMILY HOUSING

CLIENT Azria Limited, LLC
DENSITY 13 du/ac
UNIT PLAN SIZES 720-1,440 sq. ft.
TOTAL UNITS 8 du
SITE AREA 0.16 ac
STORIES 4 + roof deck garden
PARKING 10 spaces
CONSTRUCTION TYPE IIB
PROPRIETARY MODULES 24
COMPLETION DATE 2020

HOPE ON ALVARADO

PERMANENT SUPPORTIVE HOUSING (PSH)

CLIENT 166 Alvarado, LLC
DENSITY 190 du/ac
UNIT PLAN SIZES 400-480 sq. ft.
TOTAL UNITS 84 du
SITE AREA 0.44 ac
STORIES 5
PARKING 10 spaces
CONSTRUCTION TYPE IIB
PROPRIETARY MODULES 168
COMPLETION DATE Late 2019

HOPE ON LA FAYETTE

BRIDGE HOUSING FOR
THE CITY OF LOS ANGELES

CLIENT Hope Street Development
DENSITY 111 du/ac
UNIT PLAN SIZES 64-88 sq. ft.
TOTAL UNITS 72 beds
SITE AREA 0.65 ac
STORIES 1
PARKING 0 spaces
CONSTRUCTION TYPE IIB
PROPRIETARY MODULES 29 (9 unique)
COMPLETION DATE Early 2020


COST
(BRONSON > MARKET-RATE)

Approx. $300 per square foot

COST
(HOPE ON ALVARADO > PSH)

Approx. $250 per square foot*

COST
(HOPE ON LA FAYETTE)

Approx. $200 per square foot*

* Developer to advise on complete project financing


SCHEDULE

Plan Check & Approvals:
2 months

Fabrication of Modules:
2 months

Installation of Modules:
3 days

Completion of Project on Site:
4 months

SCHEDULE

Plan Check & Approvals:
3 months

Fabrication of Modules:
3 months

Installation of Modules:
12 days

Completion of Project on Site:
6 months

SCHEDULE

Plan Check & Approvals:
1 month

Fabrication of Modules:
1 months

Installation of Modules:
1 day

Completion of Project on Site:
2 months

 

To learn more information about a
specific project, CLICK one of
the project links below.