Summary-Schedule
HOPE ON ALVARADO
PERMANENT SUPPORTIVE HOUSING (PSH)
CLIENT 166 Alvarado, LLC
DENSITY 190 du/ac
UNIT PLAN SIZES 400-480 sq. ft.
TOTAL UNITS 84 du
SITE AREA 0.44 ac
STORIES 5
PARKING 10 spaces
CONSTRUCTION TYPE IIB
PROPRIETARY MODULES 168
COMPLETION DATE Mid-2020
HOPE ON LA FAYETTE
BRIDGE HOUSING (BH) FOR
THE CITY OF LOS ANGELES
CLIENT Hope Street Development
DENSITY 111 du/ac
UNIT PLAN SIZES 64-88 sq. ft.
TOTAL UNITS 72 beds
SITE AREA 0.65 ac
STORIES 1
PARKING 0 spaces
CONSTRUCTION TYPE IIB
PROPRIETARY MODULES 29 (9 unique)
COMPLETION DATE Early 2020
SCHEDULE
(HOPE ON ALVARADO > PSH)
Plan Check & Approvals:
3 months
Fabrication of Modules:
3 months
Installation of Modules:
12 days
Completion of Project on Site:
6 months
SCHEDULE
(HOPE ON LA FAYETTE > BH)
Plan Check & Approvals:
1 month
Fabrication of Modules:
1 month
Installation of Modules:
1 day
Completion of Project on Site:
2 months